Sibley East School Board approves alternate bids

2016-04-28

By Amy Newsom
Correspondent

The Sibley East School Board, at a special meeting on Monday night, April 25, approved the three alternate bids that had been tabled the week before.  


The School Board approved alternate 2 which provides an added cost to replace roofing and insulation at the shop wing in lieu of patching.  The added cost of this project is $70,700.


The School Board also approved alternate 3 which provides an added cost to replace roofing and insulation at the art/special education wing in lieu of patching.  The added cost to replace the art/special education wing is $62,600.


Finally, the School Board also approved alternate 4 which added $17,250 to electrostatically paint existing hallway lockers. 

Find the complete story in the April 28, 2016 edition of the Arlington Enterprise.